Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June ... (32019R0943)
INHALT
Regulation (EU) 2019/943 of the European Parliament and of the Council of 5 June 2019 on the internal market for electricity (recast) (Text with EEA relevance.)
- REGULATION (EU) 2019/943 OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL
- of 5 June 2019
- on the internal market for electricity
- (recast)
- (Text with EEA relevance)
- CHAPTER I
- SUBJECT MATTER, SCOPE AND DEFINITIONS
- Article 1
- Subject matter and scope
- Article 2
- Definitions
- CHAPTER II
- GENERAL RULES FOR THE ELECTRICITY MARKET
- Article 3
- Principles regarding the operation of electricity markets
- Article 4
- Just transition
- Article 5
- Balance responsibility
- Article 6
- Balancing market
- Article 7
- Day-ahead and intraday markets
- Article 8
- Trade on day-ahead and intraday markets
- Article 9
- Forward markets
- Article 10
- Technical bidding limits
- Article 11
- Value of lost load
- Article 12
- Dispatching of generation and demand response
- Article 13
- Redispatching
- CHAPTER III
- NETWORK ACCESS AND CONGESTION MANAGEMENT
- SECTION 1
- Capacity Allocation
- Article 14
- Bidding zone review
- Article 15
- Action plans
- Article 16
- General principles of capacity allocation and congestion management
- Article 17
- Allocation of cross-zonal capacity across timeframes
- SECTION 2
- Network charges and congestion income
- Article 18
- Charges for access to networks, use of networks and reinforcement
- Article 19
- Congestion income
- CHAPTER IV
- RESOURCE ADEQUACY
- Article 20
- Resource adequacy in the internal market for electricity
- Article 21
- General principles for capacity mechanisms
- Article 22
- Design principles for capacity mechanisms
- Article 23
- European resource adequacy assessment
- Article 24
- National resource adequacy assessments
- Article 25
- Reliability standard
- Article 26
- Cross-border participation in capacity mechanisms
- Article 27
- Approval procedure
- CHAPTER V
- TRANSMISSION SYSTEM OPERATION
- Article 28
- European network of transmission system operators for electricity
- Article 29
- The ENTSO for Electricity
- Article 30
- Tasks of the ENTSO for Electricity
- Article 31
- Consultations
- Article 32
- Monitoring by ACER
- Article 33
- Costs
- Article 34
- Regional cooperation of transmission system operators
- Article 35
- Establishment and mission of regional coordination centres
- Article 36
- Geographical scope of regional coordination centres
- Article 37
- Tasks of regional coordination centres
- Article 38
- Cooperation within and between regional coordination centres
- Article 39
- Working arrangements
- Article 40
- Consultation procedure
- Article 41
- Transparency
- Article 42
- Adoption and review of coordinated actions and recommendations
- Article 43
- Management board of regional coordination centres
- Article 44
- Organisational structure
- Article 45
- Equipment and staff
- Article 46
- Monitoring and reporting
- Article 47
- Liability
- Article 48
- Ten-year network development plan
- Article 49
- Inter-transmission system operator compensation mechanism
- Article 50
- Provision of information
- Article 51
- Certification of transmission system operators
- CHAPTER VI
- DISTRIBUTION SYSTEM OPERATION
- Article 52
- European entity for distribution system operators
- Article 53
- Establishment of the EU DSO entity
- Article 54
- Principal rules and procedures for the EU DSO entity
- Article 55
- Tasks of the EU DSO entity
- Article 56
- Consultations in the network code development process
- Article 57
- Cooperation between distribution system operators and transmission system operators
- CHAPTER VII
- NETWORK CODES AND GUIDELINES
- Article 58
- Adoption of network codes and guidelines
- Article 59
- Establishment of network codes
- Article 60
- Amendments of network codes
- Article 61
- Guidelines
- Article 62
- Right of Member States to provide for more detailed measures
- CHAPTER VIII
- FINAL PROVISIONS
- Article 63
- New interconnectors
- Article 64
- Derogations
- Article 65
- Provision of information and confidentiality
- Article 66
- Penalties
- Article 67
- Committee procedure
- Article 68
- Exercise of the delegation
- Article 69
- Commission reviews and reports
- Article 70
- Repeal
- Article 71
- Entry into force
- ANNEX I
- TASKS OF REGIONAL COORDINATION CENTRES
- 1. Coordinated capacity calculation
- 2. Coordinated security analysis
- 3. Creation of common grid models
- 4. Support for transmission system operators' defence and restoration plans with regard to the consistency assessment
- 5. Support the coordination and optimisation of regional restoration
- 6. Post-operation and post-disturbances analysis and reporting
- 7. Regional sizing of reserve capacity
- 8. Facilitation of the regional procurement of balancing capacity
- 9. Week-ahead to at least day-ahead regional system adequacy assessments and preparation of risk reducing actions
- 10. Regional outage planning coordination
- 11. Optimisation of inter-transmission system operator compensation mechanisms
- 12. Training and certification of staff working for regional coordination centres
- 13. Identification of regional electricity crisis scenarios
- 14. Identification of needs for new transmission capacity, for upgrade of existing transmission capacity or their alternatives
- 15. Calculation of the maximum entry capacity available for the participation of foreign capacity in capacity mechanisms
- 16. Preparation of seasonal adequacy assessments
- ANNEX II
- REPEALED REGULATION WITH LIST OF THE SUCCESSIVE AMENDMENTS THERETO
- ANNEX III
- CORRELATION TABLE
Feedback