Commission Regulation (EU) 2016/1388 of 17 August 2016 establishing a Network Cod... (32016R1388)
INHALT
Commission Regulation (EU) 2016/1388 of 17 August 2016 establishing a Network Code on Demand Connection (Text with EEA relevance)
- COMMISSION REGULATION (EU) 2016/1388
- of 17 August 2016
- establishing a Network Code on Demand Connection
- (Text with EEA relevance)
- TITLE I
- GENERAL PROVISIONS
- Article 1
- Subject matter
- Article 2
- Definitions
- Article 3
- Scope of application
- Article 4
- Application to existing transmission-connected demand facilities, existing transmission-connected distribution facilities, existing distribution systems and existing demand units used to provide demand response services
- Article 5
- Application to pump-storage power generating modules and industrial sites
- Article 6
- Regulatory aspects
- Article 7
- Multiple TSOs
- Article 8
- Recovery of costs
- Article 9
- Public consultation
- Article 10
- Stakeholder involvement
- Article 11
- Confidentiality obligations
- TITLE II
- CONNECTION OF TRANSMISSION-CONNECTED DEMAND FACILITIES, TRANSMISSION-CONNECTED DISTRIBUTION FACILITIES AND DISTRIBUTION SYSTEMS
- CHAPTER 1
- General requirements
- Article 12
- General frequency requirements
- Article 13
- General voltage requirements
- Article 14
- Short-circuit requirements
- Article 15
- Reactive power requirements
- Article 16
- Protection requirements
- Article 17
- Control requirements
- Article 18
- Information exchange
- Article 19
- Demand disconnection and demand reconnection
- Article 20
- Power quality
- Article 21
- Simulation models
- CHAPTER 2
- Operational notification procedure
- Article 22
- General provisions
- Article 23
- Energisation operational notification
- Article 24
- Interim operational notification
- Article 25
- Final operational notification
- Article 26
- Limited operational notification
- TITLE III
- CONNECTION OF DEMAND UNITS USED BY A DEMAND FACILITY OR A CLOSED DISTRIBUTION SYSTEM TO PROVIDE DEMAND RESPONSE SERVICES TO SYSTEM OPERATORS
- CHAPTER 1
- General requirements
- Article 27
- General provisions
- Article 28
- Specific provisions for demand units with demand response active power control, reactive power control and transmission constraint management
- Article 29
- Specific provisions for demand units with demand response system frequency control
- Article 30
- Specific provisions for demand units with demand response very fast active power control
- CHAPTER 2
- Operational notification procedure
- Article 31
- General provisions
- Article 32
- Procedures for demand units within a demand facility or a closed distribution system connected at a voltage level of or below 1 000 V
- Article 33
- Procedures for demand units within a demand facility or a closed distribution system connected at a voltage level above 1 000 V
- TITLE IV
- COMPLIANCE
- CHAPTER 1
- General provisions
- Article 34
- Responsibility of the demand facility owner, the distribution system operator and the closed distribution system operator
- Article 35
- Tasks of the relevant system operator
- CHAPTER 2
- Compliance testing
- Article 36
- Common provisions for compliance testing
- Article 37
- Compliance testing for disconnection and reconnection of transmission-connected distribution facilities
- Article 38
- Compliance testing for information exchange of transmission-connected distribution facilities
- Article 39
- Compliance testing for disconnection and reconnection of transmission-connected demand facilities
- Article 40
- Compliance testing for information exchange of transmission-connected demand facilities
- Article 41
- Compliance testing for demand units with demand response active power control, reactive power control and transmission constraint management
- CHAPTER 3
- Compliance simulation
- Article 42
- Common provisions on compliance simulations
- Article 43
- Compliance simulations for transmission-connected distribution facilities
- Article 44
- Compliance simulations for transmission-connected demand facilities
- Article 45
- Compliance simulations for demand units with demand response very fast active power control
- CHAPTER 4
- Compliance monitoring
- Article 46
- Compliance monitoring for transmission-connected distribution facilities
- Article 47
- Compliance monitoring for transmission-connected demand facilities
- TITLE V
- APPLICATIONS AND DEROGATIONS
- CHAPTER 1
- Cost-benefit analysis
- Article 48
- Identification of costs and benefits of application of requirements to existing transmission-connected demand facilities, existing transmission-connected distribution facilities, existing distribution systems and existing demand units
- Article 49
- Principles of cost-benefit analysis
- CHAPTER 2
- Derogations
- Article 50
- Power to grant derogations
- Article 51
- General provisions
- Article 52
- Request for a derogation by a demand facility owner, a distribution system operator or a closed distribution system operator
- Article 53
- Request for a derogation by a relevant system operator or relevant TSO
- Article 54
- Register of derogations from the requirements of this Regulation
- Article 55
- Monitoring of derogations
- TITLE VI
- NON-BINDING GUIDANCE AND MONITORING OF IMPLEMENTATION
- Article 56
- Non-binding guidance on implementation
- Article 57
- Monitoring
- TITLE VII
- FINAL PROVISIONS
- Article 58
- Amendment of contracts and general terms and conditions
- Article 59
- Entry into force
- ANNEX I
- Frequency ranges and time periods referred to in Article 12(1)
- ANNEX II
- Voltage ranges and time periods referred to in Article 13(1)
Feedback