Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code ... (32016R0631)
INHALT
Commission Regulation (EU) 2016/631 of 14 April 2016 establishing a network code on requirements for grid connection of generators (Text with EEA relevance)
- COMMISSION REGULATION (EU) 2016/631
- of 14 April 2016
- establishing a network code on requirements for grid connection of generators
- (Text with EEA relevance)
- TITLE I
- GENERAL PROVISIONS
- Article 1
- Subject matter
- Article 2
- Definitions
- Article 3
- Scope of application
- Article 4
- Application to existing power-generating modules
- Article 5
- Determination of significance
- Article 6
- Application to power-generating modules, pump-storage power-generating modules, combined heat and power facilities, and industrial sites
- Article 7
- Regulatory aspects
- Article 8
- Multiple TSOs
- Article 9
- Recovery of costs
- Article 10
- Public consultation
- Article 11
- Stakeholder involvement
- Article 12
- Confidentiality obligations
- TITLE II
- REQUIREMENTS
- CHAPTER 1
- General requirements
- Article 13
- General requirements for type A power-generating modules
- Figure 1
- Active power frequency response capability of power-generating modules in LFSM-O
- Figure 2
- Maximum power capability reduction with falling frequency
- Article 14
- General requirements for type B power-generating modules
- Figure 3
- Fault-ride-through profile of a power-generating module
- Article 15
- General requirements for type C power-generating modules
- Figure 4
- Active power frequency response capability of power-generating modules in LFSM-U
- Figure 5
- Active power frequency response capability of power-generating modules in FSM illustrating the case of zero deadband and insensitivity
- Figure 6
- Active power frequency response capability
- Article 16
- General requirements for type D power-generating modules
- CHAPTER 2
- Requirements for synchronous power-generating modules
- Article 17
- Requirements for type B synchronous power-generating modules
- Article 18
- Requirements for type C synchronous power-generating modules
- Figure 7
- U-Q/P
- max
- -profile of a synchronous power-generating module
- Article 19
- Requirements for type D synchronous power-generating modules
- CHAPTER 3
- Requirements for power park modules
- Article 20
- Requirements for type B power park modules
- Article 21
- Requirements for type C power park modules
- Figure 8
- U-Q/P
- max
- -profile of a power park module
- Figure 9
- P-Q/P
- max
- -profile of a power park module
- Article 22
- Requirements for type D power park modules
- CHAPTER 4
- Requirements for offshore power park modules
- Article 23
- General provisions
- Article 24
- Frequency stability requirements applicable to AC-connected offshore power park modules
- Article 25
- Voltage stability requirements applicable to AC-connected offshore power park modules
- Article 26
- Robustness requirements applicable to AC-connected offshore power park modules
- Article 27
- System restoration requirements applicable to AC-connected offshore power park modules
- Article 28
- General system management requirements applicable to AC-connected offshore power park modules
- TITLE III
- OPERATIONAL NOTIFICATION PROCEDURE FOR CONNECTION
- CHAPTER 1
- Connection of new power-generating modules
- Article 29
- General provisions
- Article 30
- Operational notification of type A power-generating modules
- Article 31
- Operational notification of type B, C and D power-generating modules
- Article 32
- Procedure for type B and C power-generating modules
- Article 33
- Procedure for type D power-generating modules
- Article 34
- Energisation operational notification for type D power-generating modules
- Article 35
- Interim operational notification for type D power-generating modules
- Article 36
- Final operational notification for type D power-generating modules
- Article 37
- Limited operational notification for type D power-generating modules
- CHAPTER 2
- Cost-benefit analysis
- Article 38
- Identification of costs and benefits of application of requirements to existing power-generating modules
- Article 39
- Principles of cost-benefit analysis
- TITLE IV
- COMPLIANCE
- CHAPTER 1
- Compliance monitoring
- Article 40
- Responsibility of the power-generating facility owner
- Article 41
- Tasks of the relevant system operator
- Article 42
- Common provisions for compliance testing
- Article 43
- Common provisions on compliance simulation
- CHAPTER 2
- Compliance testing for synchronous power-generating modules
- Article 44
- Compliance tests for type B synchronous power-generating modules
- Article 45
- Compliance tests for type C synchronous power-generating modules
- Article 46
- Compliance tests for type D synchronous power-generating modules
- CHAPTER 3
- Compliance testing for power park modules
- Article 47
- Compliance tests for type B power park modules
- Article 48
- Compliance tests for type C power park modules
- Article 49
- Compliance tests for type D power park modules
- CHAPTER 4
- Compliance testing for offshore power park modules
- Article 50
- Compliance tests for offshore power park modules
- CHAPTER 5
- Compliance simulations for synchronous power-generating modules
- Article 51
- Compliance simulations for type B synchronous power-generating modules
- Article 52
- Compliance simulations for type C synchronous power-generating modules
- Article 53
- Compliance simulations for type D synchronous power-generating modules
- CHAPTER 6
- Compliance simulations for power park modules
- Article 54
- Compliance simulations for type B power park modules
- Article 55
- Compliance simulations for type C power park modules
- Article 56
- Compliance simulations for type D power park modules
- CHAPTER 7
- Compliance simulations for offshore power park modules
- Article 57
- Compliance simulations applicable to offshore power park modules
- CHAPTER 8
- Non-binding guidance and monitoring of implementation
- Article 58
- Non-binding guidance on implementation
- Article 59
- Monitoring
- TITLE V
- DEROGATIONS
- Article 60
- Power to grant derogations
- Article 61
- General provisions
- Article 62
- Request for a derogation by a power-generating facility owner
- Article 63
- Request for a derogation by a relevant system operator or relevant TSO
- Article 64
- Register of derogations from the requirements of this Regulation
- Article 65
- Monitoring of derogations
- TITLE VI
- TRANSITIONAL ARRANGEMENTS FOR EMERGING TECHNOLOGIES
- Article 66
- Emerging technologies
- Article 67
- Establishment of thresholds for classification as emerging technologies
- Article 68
- Application for classification as an emerging technology
- Article 69
- Assessment and approval of requests for classification as an emerging technology
- Article 70
- Withdrawal of classification as an emerging technology
- TITLE VII
- FINAL PROVISIONS
- Article 71
- Amendment of contracts and general terms and conditions
- Article 72
- Entry into force
Feedback