COMMISSION DECISION
of 12 December 2013
on the notification by the United Kingdom of Great Britain and Northern Ireland of a transitional national plan referred to in Article 32 of Directive 2010/75/EU of the European Parliament and of the Council on industrial emissions
(notified under document C(2013) 8815)
(Only the English text is authentic)
(2013/761/EU)
Article 1
Article 2
ANNEX
Plant number used in the TNP |
Plant name |
9 |
Great Coates Works LCP 62 |
10 |
Great Coates Works LCP 63 |
11 |
Great Coates Works LCP 96 |
12 |
Grangemouth Polimeri Europa UK |
13 |
Port of Liverpool CHP — GT |
16 |
Aylesford CHP1 |
17 |
Aylesford CHP2 |
18 |
Kinneil Stack A1 (B-101) |
28 |
Burghfield Generation Site |
37 |
Cheshire CHP |
38 |
Chickerall Generation Site |
44 |
Wansborough Mill |
46 |
Didcot B Module 6 |
47 |
Dow CHP |
49 |
Dalry DSM CHP |
58 |
Ratcliffe on Soar Power Station |
68 |
Grimsby CHP1 |
71 |
Hythe CHP1 |
72 |
Hythe Package Boilers |
73 |
Indian Queens |
81 |
Keadby Power Station GT3 |
84 |
Little Barford Power Station Module 1A |
85 |
Little Barford Power Station Module 1B |
99 |
Sellafield Site Gas Turbine 1 |
100 |
Sellafield Site Gas Turbine 2 |
101 |
Sellafield Site Gas Turbine 3 |
102 |
Sellafield Site Auxiliary Boiler |
103 |
Wilton Power Station |
107 |
Solvay Interox Ltd |
120 |
INEOS Infrastructure (Grangemouth) Ltd Boilers 9 & 10 |
121 |
INEOS Infrastructure (Grangemouth) Ltd Boilers 11, 12 & 13 |
124 |
Redcar Power Station Boiler |
128 |
Wilton Olefin Boiler |
129 |
North Tees No 1 Aromatics Plant |